IGNITION SYSTEM
G-29parts diagramDistributor R/I shown for both K8 DOHC (with resonance duct, firing order 6-4-5/1-2-3 wait... cap terminal positions) and B6 DOHC. Resonance duct (callout 1) applies to K8 only. O-ring must be replaced on reinstallation.
Removal / Installation
- 1Disconnect the negative battery cable.
- 2Remove in the order shown in the figure.

- 3Install in the reverse order of removal.
- 4Adjust the ignition timing. (Refer to page G-23.)
K8 DOHC
B6 DOHC
Parts DiagramFig. fig1
| Specification | Value |
|---|---|
| Tightening torque (distributor)K8 and B6 DOHC | 19 - 25N·m |
Tightening torque (distributor)K8 and B6 DOHC
19 - 25N·m