Mazda MX-3 silhouetteMX-3

Molding

S-24prose procedure

Installation note — Windshield molding (continued)

  1. 7
    If the protector is damaged, replace it with a new one.
  2. 8
    Apply primer onto the bonding area of the glass, body, and new windshield molding by using a brush. Use only glass primer on the glass and body primer on the body and molding. Keep the area free of dirt and grease, and do not touch the surface. Allow the primer to dry for approximately 30 minutes.
    Diagram of the windshield molding/glass joint showing where to apply primer. Callouts label MOLDING (UPPER), MOLDING (SIDE), GLASS PRIMER, GLASS, and BODY PRIMER. Two molding cross-section profiles (upper and side) are shown at right.
  3. 10
    Apply a 3 mm (0.12 in) bead of repair sealant between the glass and the body.
    Diagram of applying a 3 mm (0.12 in) bead of repair sealant from a cartridge between the glass and body. Callouts label CARTRIDGE and REPAIR SEALANT, with dimension '3 (0.12)' mm (in) marked at two points.
  4. 11
    Reshape the repair sealant as shown if necessary.
    Cross-section showing the reshaped repair sealant. Callouts label GLASS, DAM, REPAIR SEALANT, and 'ADJUST SEALANT IN THIS AREA' with hatching on the sealant fillet between glass and body.
  5. 12
    Install the windshield molding before the sealant hardens. 1) Align the marks on the molding to the roof inner line. 2) Install the top of the molding. 3) Install the corners of the molding. 4) Install the sides of the molding, starting from the top and then toward the bottom.
    Windshield-perimeter installation diagram showing molding install sequence with numbered balloons 1-4 and arrows: 1 align marks to roof inner line (top center), 2 install top, 3 install corners, 4 install sides. Cut lines A and B, plus cross-section views SEC. A-A and SEC. B-B of the molding in its channel at right.
  6. 13
    Check for water leaks. If a leak is found, wipe the water off well and repeat the installation.

Hardening time of repair sealant

Hardening time of repair sealant

5°C (41°F)
Surface hardening timeApprox. 1.5 hr
Time required until car can be put into service12 hr
20°C (68°F)
Surface hardening timeApprox. 1 hr
Time required until car can be put into service4 hr
35°C (95°F)
Surface hardening timeApprox. 10 min
Time required until car can be put into service2 hr

Search Manual